Weekly workload capacity planning answers a question that a normal task list cannot: do we actually have enough time and the right people to finish the work we have promised? A realistic capacity plan accounts for meetings, leave, routine work and interruptions before you allocate project tasks. The copyable spreadsheet below shows how to calculate available project hours, find bottlenecks and make decisions about what to move before a deadline is missed. It works for a solo professional or a small team using Excel or Google Sheets.
On this page
Calculate actual capacity, not contracted hours
A person with a 40-hour workweek does not necessarily have 40 hours available for new project work. Some of the week will go to planned meetings, recurring support, administrative work, training and other responsibilities. Subtract known time away first, then recurring commitments, then a reserve for interruptions that are not already included. Avoid counting the same meeting or support shift twice. If a colleague works part time, use their actual hours rather than a standard full-time assumption.
For example, a designer has 40 scheduled hours, four hours of leave, eight hours of meetings and administration, and a four-hour reserve for unexpected requests. Their planning capacity is 24 hours. This is not a judgment about how productive the designer is. It is an estimate of how much additional planned project work can fit into the week. The Atlassian Team Playbook capacity planning guide provides a complementary exercise for discussing availability with the whole team.
Copy the weekly capacity spreadsheet
Create a sheet called Capacity and enter the following columns. Each row represents one person in one week. The amounts in the table are illustrative. Keep the original row for each week when you review the plan so you can compare forecasts with actual experience.
| Person | Scheduled | Leave | Routine | Reserve | Capacity | Assigned | Remaining |
|---|---|---|---|---|---|---|---|
| Alex | 40 | 4 | 8 | 4 | 24 | 29 | -5 |
| Morgan | 32 | 0 | 6 | 4 | 22 | 18 | 4 |
| Sam | 40 | 8 | 6 | 4 | 22 | 22 | 0 |
| Total | 112 | 12 | 20 | 12 | 68 | 69 | -1 |
With the first person on row 2, enter =MAX(0,B2-C2-D2-E2) in F2 and =F2-G2 in H2. Copy both down. To calculate the utilization of project capacity, add a column I with =IF(F2=0,"",G2/F2) and format it as a percentage. Alex is assigned about 121% of planned project capacity; Morgan is at about 82%; Sam is at 100%. The team as a whole is at about 101%. A zero-capacity row should be reviewed manually if it contains assigned work, because a percentage would be meaningless.
The numbers are deliberately small enough to audit by hand. Negative remaining hours mean a planning problem to resolve, not an instruction to work overtime. In Google Sheets, apply conditional formatting to column H to highlight negative numbers and separately flag any row with zero available capacity and positive assignments.
Estimate demand with a second sheet
Create a Work sheet with the columns Week starting, Person, Deliverable, Estimated hours, Priority, Due date and Dependency. Estimate an output that can be finished within the week, such as approving three screens, rather than an open-ended activity like improving design. If a task spans weeks, split it into realistic weekly allocations. When two people collaborate, put their own expected hours on separate rows; do not assign the full shared estimate to each person.
If the Capacity sheet represents only one week and the Work sheet contains only that same week, use =SUMIF(Work!B:B,A2,Work!D:D) in G2 to total assigned hours for the person in A2. If multiple weeks are stored together, use SUMIFS with both a person criterion and a week-start criterion. For instance, put the week-start date in J2 of Capacity and use =SUMIFS(Work!D:D,Work!B:B,A2,Work!A:A,J2). Store dates as dates and ensure names match exactly.
A useful estimate includes the time needed to review and hand off a deliverable, not just the first draft. If nobody knows whether a task will take two hours or two days, separate a short discovery task from the eventual implementation. This lets you make a smaller commitment while you gather evidence. A weighted decision matrix can help when several candidate projects compete for the same capacity.
Resolve bottlenecks before accepting more work
In the worked example, Alex is five hours over capacity while Morgan has four spare hours. If Morgan has the necessary skills and access, move four hours of suitable work from Alex to Morgan. The team would still have a one-hour gap, so defer or reduce at least one hour of work, or negotiate a different deadline. If Morgan cannot do Alex’s specialized task, the apparent spare capacity is not interchangeable. You need to change the assignment, reduce scope, or bring in help with the relevant skill.
Discuss work in this order: legally or contractually time-sensitive commitments, critical dependencies that block other people, other agreed deadlines, and optional improvements. Ask the person accountable for the trade-off to confirm the new priority. Do not simply move a task to next week without checking whether next week already has an overload. If a task must stay, identify exactly what is being displaced and tell the affected person.
Capacity is not a productivity score. A team with unused planned capacity may be protecting space for support or uncertainty. A fully allocated team may be unable to absorb even a minor incident. Choose reserves based on the nature of the work and observed variation rather than a universal utilization target.
Run a 15-minute planning review
Spend the first three minutes confirming leave, meetings and changed deadlines. Spend the next five minutes reviewing negative remaining hours and blocked deliverables. Spend another five minutes agreeing on assignments, scope changes or deferrals. In the final two minutes, record the decisions and confirm who will communicate them to stakeholders.
Do not read the entire spreadsheet aloud. Start with exceptions, and let each person flag an estimate they do not trust. The plan should make it safe to acknowledge constraints rather than rewarding unrealistic optimism. Record the resulting commitments in your meeting action items tracker so that changes have an accountable owner and date. During the week, update only material changes; the aim is to support decisions, not track every minute.
Learn from forecast errors
At the end of the week, compare planned and actual hours at the level of deliverables. For example, a six-hour task that consumed nine hours was underestimated by three hours. Investigate why: missing approval steps, an unclear specification, technical uncertainty, a dependency or a change in scope. The response might be to change the estimate for similar tasks or improve the process that creates them.
Track recurring unexpected requests separately from ordinary tasks. If a four-hour reserve routinely turns into eight hours of urgent support, adjust the next planning cycle rather than expecting people to absorb the difference. An unusually quiet week should not automatically lead to cutting the reserve; look for a pattern. Avoid using this information as an individual surveillance system. The purpose is to improve forecasting and make sustainable commitments.
Adapt the plan to your working style
For a solo professional, use one row per week and divide tasks into client work, business operations and personal commitments. For a team with specialists, add a skill or role column so you can identify bottlenecks that are invisible in the total. For teams with substantial unpredictable support work, maintain a separate duty roster and review how it affects project capacity. If you use another project management tool, keep the capacity view as a lightweight summary rather than duplicating every task.
Pair the spreadsheet with a weekly planning routine and, once the commitments fit, use time blocking to allocate execution time. Start with the coming week, review one real overload and make one concrete trade-off. The spreadsheet has done its job when it improves a decision, not when every cell is filled.
Frequently asked questions
What is the difference between workload and capacity?
Workload is the amount of work assigned. Capacity is the realistic amount of planned work that can fit into the available time and skill constraints.
What if a person has no capacity for the week?
Do not divide assigned hours by zero. Flag the row and investigate why any work is assigned during a week with no planned availability.
Should meetings count as assigned work?
They can be included as routine commitments or as specific project work, but not both. Choose a consistent convention.
How often should the spreadsheet be updated?
Review it weekly and update meaningful changes in availability, scope or deadlines during the week.
Can I use capacity planning without tracking actual hours?
Yes. Use realistic estimates and a lightweight end-of-week review. Actual hours can improve calibration, but detailed time tracking is not required for every team.